The Municipality of Anchorage, the APDEA, and the 4/10 dispute
The History Of The 4/10 Dispute
 
For more than twenty years, Anchorage’s patrol officers worked a schedule of four ten-hour days. APD’s use of a 4/10 shift was not a novelty; the majority of the country’s major police departments work 4/10’s or some other “compressed work week” schedule which call for longer daily work hours and less than five days of work per week. As with most compressed work weeks, the 4/10 schedule resulted in the same 40-hour week as a 5/8 schedule.
 
In the last week of July, 1994, Municipality announced that it intended to change to a 5/8 schedule effective September 1, 1994. The APDEA, which not been advised by the Municipality that it was even contemplating such a change, immediately asked to negotiate over the issue. The APDEA believed that the Municipality’s operational difficulties with the 4/10 shift, to the extent they existed at all, could be best addressed in a cooperative rather than a confrontational exchange. The Municipality immediately refused to negotiate over the schedule change, and reiterated its intention to change to 5/8’s on September 1, 1994.
 
In the first week of August, 1994, the APDEA filed a grievance under the “past practices” clause of its contract with the Municipality, a clause which requires both sides to negotiate before changes are made in wages, hours of work, or significant working conditions. The past practices clause contains an expedited arbitration process. Under the process, arbitration would have to be completed within a week, with the Municipality’s obligation to bargain over the issue completely and finally determined weeks before September 1, 1994, when it intended to implement the shift change.
 
Instead of proceeding to arbitration, the Municipality refused to arbitrate the grievance. This refusal resulted in the APDEA being required to file a lawsuit seeking to compel the Municipality to submit to arbitration. The Municipality vigorously resisted the lawsuit until more than two years later, in December, 1996, when it agreed to submit to arbitration.
 
Because of delays resulting from two changes in the Municipality’s choice of lawyers to handle the case, the hearing on the APDEA’s grievance was not held until Spring, 1998. The arbitrator was Janet Gaunt, widely regarded as the preeminent arbitrator in the Pacific Northwest. The arbitrator ruled that the Municipality violated the contract by changing the 20-year past practice without negotiating with the APDEA. Drawing upon negotiations history dating to the mid-1970’s, the arbitrator found that it
was clear that the Municipality and the APDEA intended that any changes in the 4/10 shift would have to be bargained before the changes were implemented, and that the 4/10 shift was part of a bargained-for-exchange with the Municipality.
 
APD returned patrol officers to the 4/10 shift in September, 1998. There remained, however, the issue of the remedy for the Municipality’s violation of the contract. Hearings on the remedy were held in Spring, 1999, with the arbitrator’s decision anticipated in July, 1999. The APDEA is seeking compensation for employees who were required to work on what should have been their days off over a four-year period, and compensation for the disruption in employees’ lives resulting from the shift change – disruption which included cancelled pre-planned vacations, alterations of college
schedules, shift changes to include child care, and the like. The remedy could be in the range of $4.0-5.0 million.
 
During the hearing on the remedy, one fact was convincingly demonstrated – there never were economic or operational reasons to change from the 4/10 to the 5/8 shift, and the shift change was made for essentially political purposes. At the time of the shift change, Mayor Mystrom announced that the move to 5/8’s would save at least $400,000 per year in overtime costs and that the shift change would be the equivalent of putting 52 new officers on the street. At the arbitration hearing, however, Municipality witnesses admitted that not only was there no support for the $400,000 figure, but that in all probability no overtime savings resulted from the shift change. The Municipality’s
witnesses also admitted that the change to 5/8’s put no more police officers on the street, and that any changes in patrol staffing were either the product of the hiring of new officers or operational changes that could have just as easily been implemented under the 4/10 shift.
 
So, when all was said and done at the arbitration hearing, the arbitrator was confronted with this set of facts:
 
(1) The Municipality’s change to a 5/8 shift was a breach of a past practice of more than 20-years’ duration, and was a clear violation of the contract;
 
(2) The APDEA protested the breach in a timely fashion, and had the Municipality proceeded to arbitration as it should have, the matter would have been resolved before the shift change was ever implement, and before the Municipality would have been exposed to any liability for damages;
 
(3) The Municipality instead refused to proceed to arbitration for years, incurring what may amount to millions of dollars of damage, before it suddenly reversed its position and agreed to the arbitration;
 
(4) The shift change seriously disrupted the lives of APDEA members and was a direct violation of the Municipality’s contractual obligations; and
 
(5) In the arbitration hearing, the Municipality spent most of its efforts showing that the reasons advanced by the Municipality for the shift change in 1994 were, in fact, false.
 
On March 17, 1999, the Arbitrator ruled that the appropriate remedy for the Municipality's violation of the contract was to compensate each patrol officer for four hours of pay for each day off on which the
officer was required to work. This remedy, which had been awarded in a prior case involving the Municipality and the IBEW, is a standard remedy in cases where employees have been forced to work on what would have been their days off.

HISTORY AND DOCUMENTATION

The History Of The 4/10 Dispute
 Arbitration Decisions APD's Original Analysis Of The 4/10 Issue
 The Municipality's Claimed $400,000 Annual Savings From Ending The 4/10 Shift The APDEA's Briefs On The Appropriate Remedy
 APDEA Settlement Offer The Mayor's Rejection Of The APDEA's
Settlement Offer